East-West Parkway

July 2010: The South Shore Tri-Town Development Corporation awarded a design-build contract to Barletta Heavy Division, Inc. (BHD) of Canton, Massachusetts to construct the eastern segment of the first phase of the East-West Parkway (Station 109+00 to Weymouth Street). Site work commenced in October 2010.

January 2011: The Massachusetts Department of Transportation awarded a design-build contract to SPS New England, Inc. (SPS) of Salisbury, Massachusetts to construct the western segment of the first phase of the East-West Parkway (Hangar 1/Shea Memorial Drive to Station 109+00).

Please contact Jim Young (Primary Contact) at 781-682-2187 x102 or Mary Cordeiro (Secondary Contact) at 781-682-2187 x100 if you have any questions or concerns related to the East-West Parkway project.

 

Exhibits

Parkway Phasing
Phase 1 Segments

 

Project Updates

2010 – Q4

BHD site work activities included:

     - Installation of erosion and sedimentation controls, clearing & grubbing, rough grading, screening and stockpiling from
        Station 109+00 to Station 128+00 (eastern boundary of the former NAS South Weymouth).

    - Construction of eastern box turtle habitat management areas 5 and 6.

    - Installation of peat settlement platforms and all pre-load fill material on the east and west sides of Old Swamp River.

    - Site housekeeping and soil stabilization prior to winter conditions/shutdown.

 

2011 – Q1

BHD site work activities included:

    - Maintenance of the site and erosion controls.

    - Monitoring (survey) of pre-load settlement three times a week.


SPS site work activities included:

    - Site survey.

    - Test pits and soil borings.

 

2011 – Q2

BHD site work activities included:

    - Clearing, installing erosion and sedimentation controls, and rough grading for the off-Base (eastern) end of the project.

    - Installation of drainage structures/features between wetlands K and L.

    - Commenced installation of wetland K and L bridges.


SPS site work activities included:

    - Installation of erosion and sedimentation controls.

    - Initial site preparation – loam stripping/stockpiling, pavement reclamation.

 

2011 – Q2

BHD site work activities included:

    - Clearing, installing erosion and sedimentation controls, and rough grading for the off-Base (eastern) end of the project.

    - Installation of drainage structures/features between wetlands K and L.

    - Commenced installation of wetland K and L bridges.


SPS site work activities included:

    - Installation of erosion and sedimentation controls.

    - Initial site preparation – loam stripping/stockpiling, pavement reclamation.

 

2011 – Q3

BHD site work activities included:

    - Commenced construction of the Old Swamp River bridge – abutments completed.

    - Completed abutments at Wetland K and Wetland L bridges.

    - Installation of all drainage structures and pipe between Wetland L and the existing detention basin in Rockland.

    - Installation of gravel borrow for roadway sub-grade and sub-base between Wetland K and 200-feet west of Weymouth Street.

    - Commenced installation of north and south mechanically stabilized earth (MSE) walls between the Old Swamp River bridge
       and Wetland K.


SPS site work activities included:

    - Preparations for abatement of Hangar 1 – utility cut & caps, temporary fencing, etc.

2011 – Q4

BHD site work activities included:

    - Removed northern sections of the four existing culverts at Old Swamp River. Commenced stream channel
       improvements and installation of gravel slopes.

    - Continued construction of MSE walls. Completed installation and backfilling at the south MSE wall
       between Old Swamp River and Wetland K.

    - Paved HMA base and binder between Wetland K and Wetland L and from Wetland L to Station 140+00.
      Paved HMA base and binder between Station 113+00 and Station 117+00.

    - Set box beams at all three bridges. Formwork and reinforcement of bridge decks substantially completed.

    - Commenced installation of light pole bases, hand holes and conduit.

    - Commenced installation of the permanent wildlife barrier fence.


SPS site work activities included:

    - Abatement of asbestos-containing materials within Hangar 1.

Project Photos

 

November 2010

 
Settlement platforms installed
Rough grading activities

 

December 2010

Installation of pre-load fill
Tackifier installed for winter
January 2011  
Pre-load area -
looking east from Sta 109+00
Parkway alignment -
looking east from Wetland K

 

February 2011

Settlement pins at pre-load area -
looking west from Sta 115+50
Parkway alignment -
looking southeast from Wetland K

 

March 2011

 
Pre-load fill – looking east from Old Swamp River
Survey monitoring pre-load settlement platforms

 

April 2011

 
Station 124+00 drainage installation
Station 123+75 flared end section and splash pad

 

May 2011

 
Station 128+00 drainage structures and pipe installation
Setting up silt bag for dewatering at wetland L bridge

 

June 2011

 
Wetland K bridge - abutment formwork and rebar
Wetland L bridge – east abutment rebar work

 

July 2011

 
Wetland L bridge – placing abutment concrete
Rockland alignment – completed gravel
sub-base – looking East

 

August 2011

 
Wetland L pedestrian bridge – forming footing
Old Swamp River bridge – placing abutment concrete;
initial MSE wall panels

 

September 2011

 
Old Swamp River bridge – finished abutment
Setting MSE wall panels

 

 
MSE wall near full height
Loam and seed installed on embankment near Station 131

 

October 2011

 
Old Swamp River Bridge – culvert removal
and restoration activities
Paving binder course

 

November 2011

 
Setting precast bridge box beams at
Old Swamp River Bridge
Installing panels at MSE Wall 4WB

 

December 2011

 
Wetland K Bridge: stay-in-place deck
formwork and rebar work
Installation of permanent wildlife barrier fence