East-West Parkway July 2010: The South Shore Tri-Town Development Corporation awarded a design-build contract to Barletta Heavy Division, Inc. (BHD) of Canton, Massachusetts to construct the eastern segment of the first phase of the East-West Parkway (Station 109+00 to Weymouth Street). Site work commenced in October 2010. January 2011: The Massachusetts Department of Transportation awarded a design-build contract to SPS New England, Inc. (SPS) of Salisbury, Massachusetts to construct the western segment of the first phase of the East-West Parkway (Hangar 1/Shea Memorial Drive to Station 109+00). Please contact Jim Young (Primary Contact) at 781-682-2187 x102 or Mary Cordeiro (Secondary Contact) at 781-682-2187 x100 if you have any questions or concerns related to the East-West Parkway project.
Exhibits Parkway Phasing
Project Updates 2010 – Q4 - Installation of erosion and sedimentation controls, clearing & grubbing, rough grading, screening and stockpiling from - Construction of eastern box turtle habitat management areas 5 and 6. - Installation of peat settlement platforms and all pre-load fill material on the east and west sides of Old Swamp River. - Site housekeeping and soil stabilization prior to winter conditions/shutdown.
2011 – Q1 - Maintenance of the site and erosion controls. - Monitoring (survey) of pre-load settlement three times a week. - Site survey. - Test pits and soil borings.
2011 – Q2 - Clearing, installing erosion and sedimentation controls, and rough grading for the off-Base (eastern) end of the project. - Installation of drainage structures/features between wetlands K and L. - Commenced installation of wetland K and L bridges. - Installation of erosion and sedimentation controls. - Initial site preparation – loam stripping/stockpiling, pavement reclamation.
2011 – Q2 - Clearing, installing erosion and sedimentation controls, and rough grading for the off-Base (eastern) end of the project. - Installation of drainage structures/features between wetlands K and L. - Commenced installation of wetland K and L bridges. - Installation of erosion and sedimentation controls. - Initial site preparation – loam stripping/stockpiling, pavement reclamation.
2011 – Q3 - Commenced construction of the Old Swamp River bridge – abutments completed. - Completed abutments at Wetland K and Wetland L bridges. - Installation of all drainage structures and pipe between Wetland L and the existing detention basin in Rockland. - Installation of gravel borrow for roadway sub-grade and sub-base between Wetland K and 200-feet west of Weymouth Street. - Commenced installation of north and south mechanically stabilized earth (MSE) walls between the Old Swamp River bridge - Preparations for abatement of Hangar 1 – utility cut & caps, temporary fencing, etc. 2011 – Q4 - Removed northern sections of the four existing culverts at Old Swamp River. Commenced stream channel - Continued construction of MSE walls. Completed installation and backfilling at the south MSE wall - Paved HMA base and binder between Wetland K and Wetland L and from Wetland L to Station 140+00. - Set box beams at all three bridges. Formwork and reinforcement of bridge decks substantially completed. - Commenced installation of light pole bases, hand holes and conduit. - Commenced installation of the permanent wildlife barrier fence.
- Abatement of asbestos-containing materials within Hangar 1.