July 2010: The South Shore Tri-Town Development Corporation awarded a design-build contract to Barletta Heavy Division, Inc. (BHD) of Canton, Massachusetts to construct the eastern segment of the first phase of the East-West Parkway (Station 109+00 to Weymouth Street). Site work commenced in October 2010.

January 2011: The Massachusetts Department of Transportation awarded a design-build contract to SPS New England, Inc. (SPS) of Salisbury, Massachusetts to construct the western segment of the first phase of the East-West Parkway (Hangar 1/Shea Memorial Drive to Station 109+00).

Please contact Jim Young (Primary Contact) at 781-682-2187 x102 or Mary Cordeiro (Secondary Contact) at 781-682-2187 x100 if you have any questions or concerns related to the East-West Parkway project.

 

Exhibits

Parkway Phasing
Phase 1 Segments

 

Project Updates

2010 – Q4
BHD site work activities included:

- Installation of erosion and sedimentation controls, clearing & grubbing, rough grading, screening and stockpiling from Station 109+00 to Station 128+00 (eastern boundary of the former NAS South Weymouth).

- Construction of eastern box turtle habitat management areas 5 and 6.

- Installation of peat settlement platforms and all pre-load fill material on the east and west sides of Old Swamp River.

- Site housekeeping and soil stabilization prior to winter conditions.

 

Project Photos

November 2010  
Settlement platforms installed
Rough grading activities

 

December 2010

Installation of pre-load fill
Tackifier installed for winter